Technical guide: design and consulting
Input data, analyses, deliverables, and normative references for the 21 Sky Meridian services: airport infrastructure, AACR permitting, roads, water and sewerage, construction, consulting, and investment management.
The guide is addressed to beneficiaries and specialists preparing projects in Bihor and across Romania. Each chapter defines the technical scope of the service and the information required to define a contractual brief.
Normative references are selected based on object, site, phase, organization domain, and application date. A list of acts does not replace the project requirements registry or the verification of applicable editions.
Design basis and regulatory applicability
A requirements registry is drawn up for each project, allowing for the tracking of links between references, calculations, documents, and verification. The registry is updated under control when the brief, configuration, or applicable framework changes.
- Reference identification: issuer, code, edition, revision, amendments, and approval act, where applicable.
- Applicability: object, phase, domain, and date of application; transitional provisions and the reason for the inclusion or exclusion of the requirement are noted.
- Demonstration: the relevant article or criterion is associated with input data, calculation method, result, and the document constituting proof.
- Data control: source, revision, coordinate system, elevation datum, units, precision, and limitations; conversions and assumptions are explicit.
- Responsibilities: author, checker, data owner, and the body that accepts, permits, or approves, according to the applicable framework.
In the field of aerodromes, a distinction is made between mandatory regulations, CS specifications from the certification basis, acceptable means of compliance (AMC), and guidance material (GM). Technical or industry standards incorporated by contract are identified separately. The existence of a new edition does not, in itself, establish its applicability to an already certified configuration.
Airport terminology: "design aircraft" is used, identifying the type, variant, and parameters determining the verification performed. The aerodrome classification, aircraft geometry, pavement loading, and operating conditions are explicitly correlated.
Regulatory updates: for urban planning and construction, check Law no. 169/2026 — The Code of Spatial Planning, Urbanism, and Construction and transitional situations. For aeronautical permitting, RACR-AVZ is used in consolidated form, including the 2026 amendments. Historical references from existing documentation are not adopted automatically.
1. Water, sewerage, and utility installations
The sizing of water supply, sanitary sewerage, and rainwater drainage networks is based on flow balances, operating regimes, and connection conditions. The solution is correlated with vertical systematization, geotechnics, and the capacity of the receiving infrastructure.
Input data
Topographic survey, geotechnical study, utility inventory, permits and data from operators, population or equivalent consumers, technological consumption, collection areas, hydrological conditions, and discharge levels. The source, date, and units of each data set are specified.
Technical analyses and checks
- Water: determination of design flows, pressure losses, and nodal pressures; verification of consumption scenarios and, where relevant, fire scenarios; pump selection based on the duty point and transient regime analysis if configuration requires.
- Sewerage: sizing of gravity and pressure collectors, verification of slopes, velocities, and degree of filling; evaluation of backwater, rainwater retention, and discharge flow limitation.
- Constructive: invert and cover levels, intersections with utilities, crossings, shoring, and dewatering; stability verification of buried structures and operational conditions.
Deliverables
Specialty reports, hydraulic summary, site plans and longitudinal profiles, pumping schemes, constructive details, technical specifications, quantities, and interference matrix. Calculation assumptions and verified scenarios are identifiable in the documentation.
Normative basis and scope
- NP 133-2022, vol. I — water supply systems; MDLPA Order no. 15/2023 — Water supply networks and systems.
- NP 133-2022, vol. II — sewerage systems; MDLPA Order no. 14/2023 — Sewerage systems and related components.
- NP 133-2022, vol. III — hydro-utility structures; MDLPA Order no. 19/2023 — Reinforced or prestressed concrete hydro-utility structures, if within the project object.
- I9-2022 — building plumbing installations; MDLPA Order no. 2,960/2022 — Building plumbing installations; delimitation from public networks.
Foundational condition: The boundary between external networks and building installations, data guaranteed by the operator, and the discharge regime. Solutions for gas, energy, or other utilities are addressed only within the contracted scope, with the necessary specialists and authorizations.
Sky Meridian Service: Water, sewerage, and utility installations · Back to contents
Practical article: Water and sewerage design: what to prepare before the project
2. Roads, accesses, and parking lots
The design of roads, accesses, and parking lots correlates route geometry, design traffic, pavement structure, and water drainage. The road regime and relationship with the infrastructure administrator to which it connects are established from the beginning.
Input data
Topography, cadastre and property boundaries, geotechnical study, existing and forecast traffic, design vehicle, road category and function, road system surveys, drainage status, and intersected networks.
Technical analyses and checks
- Geometry: plan route, longitudinal profile, cross-sections, visibility, slopes, and connections; verification of design vehicle maneuvers at intersections, accesses, and parking lots.
- Pavement structure: design traffic and perspective period, foundation soil and material characteristics, dimensioning checks, and behavior regarding water and frost, according to the adopted solution.
- Drainage and phasing: platform runoff, ditches, gutters, culverts, and discharges; maintenance of access and traffic organization during works.
Deliverables
Route justification report, pavement structure dimensioning summary, plans and profiles, drainage and connection details, signage, technical specifications, and quantities.
Normative basis and scope
- MT Order no. 1,296/2017 — design, construction, and modernization of roads — Geometric and functional requirements, within the scope of the order.
- AND 605-2016 — hot-mixed asphalt — Composition and requirements for hot-mixed asphalt; does not replace pavement structure dimensioning.
- NP 074-2022 — geotechnical documentation for construction; MDLPA Order no. 27/2023 — Geotechnical foundation of the solution.
- HG no. 907/2016 — technical-economic documentation for public-funded investments — Content of technical-economic phases, if financing falls under the decision.
Foundational condition: A public road, a private access, and an airport service road do not automatically have the same design basis. For roads in the operational area, interfaces with aerodrome safety are added.
Sky Meridian Service: Roads, accesses, and parking lots · Back to contents
Practical article: Road design: necessary data and documentation phases
3. Civil engineering
Design coordinates architecture, structure, and installations through verifiable performance requirements. For existing buildings, the solution is based on surveys, investigations, and the technical expertise required for the intervention.
Input data
Functional brief, urban planning and authorization documents, topography and geotechnics, project importance class and category, surveys, technological loads, fire requirements, and utility connection conditions.
Technical analyses and checks
- Structure and foundations: calculation model, actions and combinations, verification for ultimate and serviceability limit states, displacements, stability, and deformation compatibility; geotechnical parameters are correlated with investigations.
- Architecture and fire safety: functional organization, circulation, evacuation, compartmentalization, and performance of elements; coordination with the fire safety scenario, when necessary.
- Installations and envelope: openings and routes, supplies, evacuations, electrical protections, crossing seals, thermal bridges, and maintenance access; resolving incompatibilities before issuing drawings.
Deliverables
Reports, summaries, and calculation models, coordinated drawings, details, performance specifications, quantities, and documents for project technical verification, according to the contracted phase.
Normative basis and scope
- Law no. 169/2026 — The Code of Spatial Planning, Urbanism, and Construction — Framework for urban planning, authorization, and quality, with analysis of transitional situations.
- NP 074-2022 — geotechnical documentation for construction; MDLPA Order no. 27/2023 — Geotechnical documentation.
- P 100-1/2013 — seismic design of buildings; Order no. 2,465/2013 — Seismic design within the scope of P 100-1; interventions are treated according to the specific framework for existing buildings.
- P 118/1-2025 — fire safety of buildings; MDLPA Order no. 267/2025 — Fire safety, according to project function and situation.
- I9-2022 — building plumbing installations; MDLPA Order no. 2,960/2022 — Plumbing installations.
- I 7-2011 — electrical installations in buildings; amendments via Order no. 959/2023 — Electrical installations in buildings.
Foundational condition: The normative registry separately specifies applicable structural standards and national annexes. For ventilation, HVAC, and fire protection installations, the standards for the effectively included specialties are supplemented.
Sky Meridian Service: Civil engineering · Back to contents
Civil engineering design: brief, documents, and specialty coordination: practical article for project preparation.
4. Airports and airport infrastructure
The design brief establishes the design aircraft, operational scenarios, and aerodrome certification basis. Design aircraft parameters are documented for each verification; the aircraft determining geometry may differ from the one determining pavement structure loading.
Input data
Certificate and certification basis, aerodrome configuration, AIP, measurements and terrain model, geotechnics, design aircraft data, traffic scenarios, CNS/MET facilities, and operational limitations during works.
Technical analyses and checks
- Geometry: wingspan, outer main gear wheel span, wheelbase, and turn geometry; clearances, safety distances, and taxi routes. Turnaround pads and parking positions are verified for the maneuvers actually envisaged.
- Infrastructure: load-bearing capacity, surfaces and slopes, drainage, shoulders, strip, RESA, and stopway, depending on the work object. For stopways, the function, constructive characteristics, and declared distances are correlated.
- Operation: markings, lighting, and signage, jet blast effects, vehicle access, FOD, and CNS interference. Phasing includes unavailable areas, temporary obstacles, separations, and reopening conditions.
Deliverables
Design basis, compliance report for applicable CS, summaries, plans and details, interface matrix, change management documentation, and data for updating aeronautical information, within contract limits.
Normative basis and scope
- Regulation (EU) no. 139/2014 — EASA official register of regulations for aerodromes — Regulation (EU) no. 139/2014: certification, organization, and operation.
- CS-ADR-DSN, Issue 7 — certification specifications for aerodrome design — Geometry and infrastructure, according to the certification basis.
- RACR-AVZ, edition 2/2020 — Order no. 893/2020, consolidated form — Technical documentation permitting, according to object and site.
- RACR-ZSAC, edition 1/2015 — MT Order no. 735/2015, as amended — Protection of the aerodrome and CNS/MET facilities.
Foundational condition: CS-ADR-DSN is not applied by simply choosing the newest edition: the reference is correlated with the certification basis and the proposed change. The national regime is analyzed separately for aerodromes outside the European scope.
Documented experience: Reconfiguration of apron no. 1 — Oradea; Aircraft hangars — Oradea; Turnaround pads, stopway, and shoulders — Oradea. Team contribution and documentation phase are specified in the case studies.
Sky Meridian Service: Airports and airport infrastructure · Back to table of contents
Airport design: from reference aircraft to work phasing: practical article for project preparation.
5. Urban Planning: PUG, PUZ, and PUD
Urban planning documentation is established in relation to approved regulations, the proposed development, and the legal framework applicable at the initiation and resolution of the procedure. In the context of the 2026 amendments, the classification of the instrument and the content of the documentation are reconfirmed prior to contracting.
Input data
Cadastral boundaries, land deeds, approved urban planning documentation, local regulations, building restrictions, utility network capacity, accessibility, protection zones and servitudes, as well as the status of any initiated procedures.
Technical analyses and checks
- Territorial diagnosis: land use, circulation, utilities, natural and technological risks, heritage, and environment; identification of incompatibilities with the investment.
- Regulation: functions, indicators, heights, setbacks, access, and building equipment, at the level allowed by the applicable instrument; correlation of plans with the regulation and balance sheets.
- Permitting: inventory of required permits and studies, traceability of observations, and integration of aeronautical restrictions when the site is affected by them.
Deliverables
Report and supporting studies included in the brief, analysis and regulation plans, associated regulation, territorial balance sheets, documents for permitting, and revision records.
Normative basis and scope
- Law no. 169/2026 — The Code for Territorial Planning, Urbanism, and Construction — The 2026 Code and transitional provisions; procedures and secondary acts are identified for the specific instrument.
- RACR-ZSAC, edition 1/2015 — MT Order no. 735/2015, as amended — Integration of zones with aeronautical servitudes, where applicable.
- RACR-AVZ, edition 2/2020 — Order no. 893/2020, consolidated version — Documentation subject to aeronautical permitting.
Grounding condition: Urban approval and AACR (Romanian Civil Aeronautical Authority) permit have distinct objectives. Urban height allowance alone does not demonstrate the aeronautical acceptability of a construction.
Sky Meridian Service: Urban Planning: PUG, PUZ, and PUD · Back to table of contents
PUG, PUZ, and PUD: what to check before preparing urban planning documentation: practical article for project preparation.
6. Investment Planning and Preparation
Investment preparation transforms the beneficiary's need into capacities, performance requirements, technical alternatives, and acceptance criteria. The level of detail must support the investment decision and the subsequent phase.
Input data
Justified need, legal and technical status of the site, existing capacities, estimated demand, source of funding, operational restrictions, available studies, and dependencies on other investments.
Technical analyses and checks
- Defining the brief: functions, capacities, performance, and intervention limits; each requirement is linked to a justification and a verification method.
- Comparing alternatives through technical feasibility, investment, operation, maintenance, risks, and phasing; estimation uncertainties are explicitly retained.
- Planning studies, permits, design, and procurement; monitoring interfaces that may alter the solution, cost, or timeline.
Deliverables
Conceptual note and brief, pre-feasibility study when necessary, Feasibility Study (SF) or DALI as appropriate, comparative analysis, estimate and budget according to the phase, schedule, and risk register.
Normative basis and scope
- GD no. 907/2016 — technical-economic documentation for investments financed from public funds — Stages and framework content for investments financed from public funds.
- Law no. 169/2026 — The Code for Territorial Planning, Urbanism, and Construction — Urban planning and authorization conditions.
- Regulation (EU) no. 139/2014 — official EASA register of aerodrome regulations — For airport investments: integration of certification requirements and change management.
Grounding condition: SF and DALI are not interchangeable. Classification is based on the nature of the objective and the intervention; for mixed projects, components are delimited.
Sky Meridian Service: Investment Planning and Preparation · Back to table of contents
Investment preparation: from need to conceptual note and design brief: practical article for project preparation.
7. Documentation for AACR Permitting
Documentation for AACR permitting must unambiguously describe the location, dimensions, and characteristics of the objective. The assessment correlates geometric, operational, and radio-electric effects, depending on the affected aeronautical zones.
Input data
Urban planning certificate and required legal data, coordinates and elevations with specified reference systems, measurements by authorized specialists, location and site plans, sections, elevations, and report. Elements on the roof and relevant temporary clearances, such as cranes, are included.
Technical analyses and checks
- Verifying site identity across all documents, ground elevation, height, and maximum absolute elevation. Planimetric and altimetric conversions are documented.
- Identifying affected surfaces and zones: geometric obstruction, flight procedures, CNS/MET facilities, and aerodrome development. Additional studies are delimited according to AACR requirements.
- Compiling the file for the requested phase and responding to observations in a traceable manner. Changes in position, volume, or height are verified against permit conditions and the current RACR-AVZ format.
Deliverables
Application and technical documentation, inventory of coordinates, correlated plans and reports, contracted supporting studies, table of responses to observations, and record of permit conditions.
Normative basis and scope
- RACR-AVZ, edition 2/2020 — Order no. 893/2020, consolidated version — RACR-AVZ, including item 2.4 regarding documentation structure and content.
- AACR DG Decision no. D306/26.06.2020 — documentation requirements and annexes — Decision D306/26.06.2020 and annexes applicable to the application and studies.
- RACR-ZSAC, edition 1/2015 — MT Order no. 735/2015, as amended — Identification of relevant zones and restrictions.
- MTI Order no. 778/2026 — amending RACR-AVZ — 2026 amendments regarding authorized configuration and update conditions.
Grounding condition: The consultant prepares the technical support; AACR issues the permit and establishes conditions. The file must distinguish between the geometric study, shading study, and radio-electric compatibility assessment.
Sky Meridian Service: Documentation for AACR Permitting · Back to table of contents
Practical article: AACR Permit: what documents to prepare before submission
8. Obstacle Limitation Studies and Aeronautical Data
The analysis distinguishes between geometric obstruction and effects on flight procedures or radio-electric compatibility. Fitting under a geometric surface does not, by itself, demonstrate the absence of an effect on ILS or other CNS facilities.
Input data
Geodetic data and metadata, terrain model, existing and proposed objectives, maximum height and their configuration, applicable aeronautical surfaces, and data provided by CNS facility managers. For ILS, the localizer (LOC) and glide path (GP) are identified separately.
Technical analyses and checks
- Obstruction: modeling OLS surfaces and, where applicable, OFZ; calculating penetrations with consistent elevations and conventions; inventory of permanent and temporary obstacles. The effect on flight procedures is addressed through appropriate specialized evaluation.
- Geometric shading: justifying the relationship between the objective and existing obstacles admitted as reference, according to applicable criteria. The mere fact that one building is behind another is not sufficient demonstration.
- ILS and CNS: analysis of position relative to antennas, protection zones, and relevant critical/sensitive areas, geometry, materials, and mobile configurations. Electromagnetic shading is delimited from reflections, diffraction, and multipath propagation; a preliminary geometric check alone does not quantify signal degradation.
- When demonstrating radio-electric effect is necessary, the model, manufacturer data, scenarios, and acceptance criteria are established with AACR and the facility manager. The need for simulations, measurements, or flight inspections results from the applicable assessment.
Deliverables
Obstacle report, plans and sections, inventory of coordinates and elevations, penetration table, assumptions, and limitations. The CNS component explicitly specifies whether the deliverable is a preliminary geometric check or a radio-electric compatibility study based on modeling or measurements.
Normative basis and scope
- RACR-ZSAC, edition 1/2015 — MT Order no. 735/2015, as amended — Zones with aeronautical servitudes and protection of CNS/MET facilities.
- AACR DG Decision no. D306/26.06.2020 — documentation requirements and annexes — Annexes 4 and 5 for the content of geometric studies, in required situations.
- AACR-DANA-MET-CNS-02 — methodology for radio-electric compatibility assessment — AACR-DANA-MET-CNS-02: methodological reference for radio-electric compatibility, with verification of the controlled edition.
- CS-ADR-DSN, Issue 7 — certification specifications for aerodrome design — Surfaces and associated obstruction requirements for the certification basis.
Grounding condition: For the DANA methodology, the applicable controlled copy is required. Edition 2/2018 is identified in the consulted AACR bibliography, but the current revision and full text must be confirmed before using criteria or thresholds from the procedure.
Sky Meridian Service: Obstacle Limitation Studies and Aeronautical Data · Back to table of contents
Obstacle limitation studies: data required for OLS, CNS, and shading analysis: practical article for project preparation.
9. AIP Updates
AIP updating aims for consistency between the authorized or approved configuration, the measured situation, and the published information. Data preparation and publication via the aeronautical information service are distinct responsibilities.
Input data
AIP and current amendments, measured data, approved plans, operational decisions, coordinates and elevations, declared distances, characteristics of surfaces and equipment, proposed entry-into-service date.
Technical analyses and checks
- A record of changes is maintained, and text, tables, charts, and datasets are cross-checked; each value has an identifiable origin, unit, precision, and responsible party.
- Conversions, rounding, transfer integrity, and revisions are controlled. For declared distances or modified coordinates, technical documents justifying the values are retained.
- Handover is coordinated with the AIS provider, including the AIRAC calendar where applicable and the choice of the appropriate information product according to the nature and duration of the change.
Deliverables
Package of data and proposed text, plans or charts in the required format, verification report, source-value-publication matrix, and record of acceptance or received observations.
Normative basis and scope
- Regulation (EU) 2017/373 — ATM/ANS framework and aeronautical information services — Regulation (EU) 2017/373, AIS requirements, and data provision agreements.
- Regulation (EU) no. 139/2014 — official EASA register of aerodrome regulations — Regulation (EU) no. 139/2014, Part-ADR.OPS.A: aeronautical data and information coordination.
Grounding condition: Transmitting a data package does not equate to publication or approval of the operation of the modified configuration. Timelines are coordinated with data provision agreements.
Sky Meridian Service: AIP Updates · Back to table of contents
AIP updating: how to prepare data and the AIRAC calendar: practical article for project preparation.
10. Aircraft Compatibility with the Aerodrome
Compatibility is demonstrated for the reference aircraft, its configuration, and the analyzed operational scenario. The aerodrome reference code is a classification benchmark; the evaluation must cover all constraints relevant to the operation.
Input data
Manufacturer data for the aircraft variant, wingspan, length, wheelbase, main gear track, turning dimensions, weights, and gear characteristics; measured infrastructure, published load-bearing capacity, obstacles, service facilities, and operating conditions.
Technical analyses and checks
- Geometry: trajectories and swept paths, edge and object clearances, taxiway/apron/stand separations; verifying access and exit in the effective configuration.
- Structure and operation: aircraft load compared to available bearing capacity in the applicable reporting system; weights and operational frequencies, jet blast effects, restrictions, and protection measures.
- Interfaces: rescue and firefighting, handling, towing, fueling, equipment parking, and potential influences on CNS. Compensatory measures are evaluated and assigned to responsible parties.
Deliverables
Compatibility report, maneuver plans, requirement-verification-result matrix, proposed restrictions, and safety assessment associated with the change, as applicable.
Normative basis and scope
- Regulation (EU) no. 139/2014, Annex IV — Part-ADR.OPS, operational requirements — ADR.OPS.B.090 and relevant operational requirements.
- CS-ADR-DSN, Issue 7 — certification specifications for aerodrome design — Geometric and infrastructure criteria, according to the certification basis.
- Regulation (EU) no. 139/2014, Annex III — Part-ADR.OR — ADR.OR.B.040: changes and associated assessments.
Grounding condition: For use by aircraft exceeding certified design characteristics, the approval procedure in ADR.OPS.B.090 must be verified. Acceptability is established for documented conditions, not for any operation of the respective type.
Sky Meridian Service: Aircraft Compatibility with the Aerodrome · Back to table of contents
Aircraft compatibility: how to prepare the evaluation for an aerodrome: practical article for project preparation.
11. AltMoC, ELOS, and Special Conditions
AltMoC, ELOS, and special conditions have different functions and procedures. Classification is based on the regulatory requirement, the target AMC or certification specification, and the reason why the standard solution does not cover the situation.
Input data
The exact requirement and its edition, the certification basis, the existing or proposed situation, the technical demonstration, relevant operational experience, and the limits within which the use of the solution is requested.
Technical analyses and verifications
- AltMoC: describes the alternative means to the AMC and demonstrates that the regulatory requirement is met; includes the affected procedures and manual revisions.
- ELOS: formulates the demonstration of an equivalent level of safety for the alternative to the certification specification, with assumptions, arguments, evidence, and conditions of use.
- Special conditions: documents the characteristic for which the CS are inadequate or unsuitable; the competent authority establishes the special conditions and their integration into the certification basis.
Deliverables
Classification memorandum, compliance matrix, technical and safety demonstration, operational conditions, revised documents, and response package to authority observations.
Regulatory basis and scope
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR — ADR.OR.A.015: means of compliance.
- Regulation (EU) No 139/2014, Annex II — Part-ADR.AR — ADR.AR.C.020(b): ELOS in the certification basis; ADR.AR.C.025: special conditions.
Foundational condition: A favorable risk assessment does not automatically transform a non-compliance into an approved AltMoC or ELOS. Implementation follows the applicable procedure and approvals.
Sky Meridian Service: AltMoC, ELOS and special conditions · Back to table of contents
AltMoC, ELOS and special conditions: how to choose the mechanism and prepare the dossier: practical article for project preparation.
12. Operational, technical, and safety consulting
Technical and operational consulting starts from an identified configuration and a measurable problem: capacity, availability, restriction, change, or non-compliance. The assessment tracks the interdependencies between infrastructure, procedures, and organizations.
Input data
Certification basis, aerodrome manual, procedures, traffic data, inspection reports, occurrences, supplier contracts, and current technical configuration.
Technical analyses and verifications
- Delimits the analyzed system, scenarios, and acceptance criteria; findings are separated from assumptions requiring additional data.
- Compares solutions by operational effect, compliance, resources, residual risk, and maintenance; includes effects on organizations using the same infrastructure.
- Plans the implementation and effectiveness verification of measures, including procedure modification, training, and aeronautical data updates when affected.
Deliverables
Technical report, options analysis, contracted assessments, implementation plan with owners and deadlines, validation criteria, and monitoring conditions.
Regulatory basis and scope
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR — Part-ADR.OR: management system, changes, and contracted activities.
- Regulation (EU) No 139/2014, Annex IV — Part-ADR.OPS, operational requirements — Part-ADR.OPS: analyzed operational processes.
- CS-ADR-DSN, Issue 7 — certification specifications for aerodrome design — Reference for issues affecting physical configuration.
Foundational condition: The scope of the consulting must be separated from operator responsibilities, certified supplier activities, and AACR decisions.
Sky Meridian Service: Operational, technical, and safety consulting · Back to table of contents
Airport consulting: from operational diagnosis to a verifiable action plan: practical article for project preparation.
13. Compliance monitoring and SMS
Compliance monitoring verifies adherence to applicable requirements. The safety management system identifies hazards, assesses risks, and tracks the effectiveness of measures. The two processes are correlated through evidence, without substituting one another.
Input data
Requirements register, organization structure, manuals, monitoring program, previous findings, occurrence reports, hazard register, planned changes, and indicators used.
Technical analyses and verifications
- Compliance: planning audits based on domain and risk, evidence sampling, formulating findings against requirements, and tracking corrective actions.
- SMS: description of the hazard and consequences, assessment of initial and residual risk through the organization's approved method, assignment of measures, and documentation of risk acceptance.
- Effectiveness: root cause analysis, implementation verification, and outcome testing; indicators have definitions, data sources, thresholds, and owners.
Deliverables
Monitoring program and reports, findings register, action plans, safety assessments, hazard register, and management reports, within the limits of contracted services.
Regulatory basis and scope
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR — ADR.OR.D.005: management system; ADR.OR.B.040: change management; ADR.OR.C.020: findings and corrective actions.
- Part-ADR.OR — records, coordination, manual and training programs — Records, coordination, and document traceability.
Foundational condition: Administrative closure of an action does not demonstrate its effectiveness. Evidence must show both implementation and the effect on the targeted requirement or risk.
Sky Meridian Service: Compliance monitoring and SMS · Back to table of contents
Compliance and SMS: how to link audits, risks, and corrective actions: practical article for project preparation.
14. Handling and fuel handling audits
Handling and fuel handling audits evaluate processes and evidence against stated criteria. Criteria may originate from requirements applicable to the aerodrome operator, supplier authorizations, and contractually assumed standards.
Input data
Scope of services and locations, authorizations, contracts, procedures, personnel competence, equipment inventory, maintenance, occurrence reports, and for fuel, reception documents, traceability, and quality control.
Technical analyses and verifications
- Handling: observation of aircraft operations, equipment positioning, collision and FOD prevention, communication, airport interfaces, and compliance with equipment limits.
- Fuel: documented quality chain, reception and storage, checks and sampling prescribed by applicable procedures, filtration, equipment, refueling, and prevention of contamination or fire.
- Findings: requirement, evidence, deviation, consequence, and owner; distinguishes immediate correction from root cause action.
Deliverables
Audit plan and checklist, report with evidence, prioritization of findings, action plan, and closure verification. JIG/EI or beneficiary standards are identified with the contractual edition if they are part of the audit criteria.
Regulatory basis and scope
- Regulation (EU) No 139/2014, Annex IV — Part-ADR.OPS, operational requirements — Part-ADR.OPS: operational processes and interfaces, including fuel quality within the operator's domain.
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR — ADR.OR.D.010: contracted activities and responsibilities.
- EASA — Easy Access Rules for Aerodromes, March 2026 revision — Identification of application data for European changes for handling.
Foundational condition: A consulting audit is not equivalent to a JIG/EI certification. New European requirements for handling with application from March 27, 2028, are tracked separately from obligations applicable in 2026.
Sky Meridian Service: Handling and fuel handling audits · Back to table of contents
Handling and fuel audit: the documents and verifications that matter: practical article for project preparation.
15. Airport procedures and manuals
Manuals and procedures must describe the configuration and the actual way of operating. A revision has an object, owner, trigger criteria, sequence of actions, and records that allow for the verification of implementation.
Input data
Applicable requirements, approved manual, existing processes and workflows, interfaces with ATS/CNS and suppliers, technical limitations, relevant occurrences, and planned changes.
Technical analyses and verifications
- Constructs the requirement–procedure–owner–record matrix; verifies activity coverage and the elimination of contradictions between documents.
- Defines thresholds and conditions for normal, degraded, and emergency operations; procedures specify communication, restrictions, and authorization for returning to normal.
- Validates applicability through walkthroughs, exercises, or field observations, according to the process; controlled distribution and training are planned in conjunction with entry into force.
Deliverables
Revised manual or procedures, process diagrams when useful, forms, compliance matrix, revision history, and implementation package.
Regulatory basis and scope
- Part-ADR.OR — records, coordination, manual and training programs — ADR.OR.E.005: aerodrome manual; ADR.OR.D.035: record-keeping.
- Regulation (EU) No 139/2014, Annex IV — Part-ADR.OPS, operational requirements — Operational requirements corresponding to each procedure.
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR — ADR.OR.B.040: changes requiring approval or management through the accepted procedure.
Foundational condition: Editorial revision, internal approval, and approval or notification to the AACR are distinguished based on the type of change and the applicable requirement.
Sky Meridian Service: Airport procedures and manuals · Back to table of contents
Airport procedures: how to transform requirements into applicable instructions: practical article for project preparation.
16. Training in the airport domain
The training program is defined starting from job responsibilities and necessary competencies, not just from a list of topics. The evaluation must show that the individual can apply the relevant procedures under the intended operating conditions.
Input data
Job descriptions, competence matrix, local procedures, equipment types, training history, competence assessment results, and changes affecting the activity.
Technical analyses and verifications
- Establishes observable objectives, access conditions, theoretical and practical content, instructor qualifications, and evaluation method.
- Differentiates between initial, periodic, refresher, and change-associated training, depending on the applicable requirement and the organization's program.
- Verifies application in relevant scenarios and defines criteria for promotion, remediation, and re-verification.
Deliverables
Adapted program and materials, practical scenarios, evaluation tools, results, participation and competence records, plus recommendations for supplementing the local program.
Regulatory basis and scope
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR — ADR.OR.D.017: training and competence assessment programs, with applicable AMC/GM.
- Part-ADR.OR — records, coordination, manual and training programs — Records and integration of the program into the operator's documentary system.
Foundational condition: Course attendance and demonstration of competence are different outcomes. The issued document must describe exactly the training and assessment performed, without suggesting an authorization that is not included.
Sky Meridian Service: Training in the airport domain · Back to table of contents
Airport training: how to build a competency-based program: practical article for project preparation.
17. Assistance for aerodrome certification
Assistance for certification organizes the compliance demonstration for the aerodrome and the operator. The starting point is the scope of the application and the certification basis established by the competent authority.
Input data
Application and AACR correspondence, certification basis, aerodrome plans and data, organization documents, manual, procedures, training records, and list of open findings.
Technical analyses and verifications
- Develops the compliance matrix with links to identifiable and current evidence; separates physical configuration compliance from organizational and operational requirements.
- Identifies differences between documents and the field, gaps in evidence, and cases requiring ELOS, special conditions, or other applicable mechanisms.
- Prepares inspections and demonstrations, tracks responses to findings, and verifies the integration of restrictions into the manual and operational data.
Deliverables
Compliance file, requirement–evidence matrix, remediation plan, revised documents, record of responses, and support for technical interaction with the AACR.
Regulatory basis and scope
- Regulation (EU) No 139/2014, Annex II — Part-ADR.AR — Part-ADR.AR, especially the certification basis and the certificate issuance process.
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR — Part-ADR.OR: application, compliance demonstration, and changes.
- CS-ADR-DSN, Issue 7 — certification specifications for aerodrome design — Criteria for physical configuration, in accordance with the certification basis.
Basis condition: The issuance or modification of the certificate belongs to the competent authority. The support service cannot guarantee a decision independent of the demonstration of compliance.
Sky Meridian Service: Assistance for aerodrome certification · Back to table of contents
Aerodrome certification: how to organize the file and the demonstration of compliance: practical article for project preparation.
18. Hardware and software solutions
Solutions for monitoring, records, and automation of aerodrome processes are specified through verifiable requirements regarding data, availability, security, and fail-safe behavior. The applicability of aeronautical requirements depends on the function and use of the system.
Input data
Processes, users and roles, data sources, interfaces, volumes, precision and acquisition intervals, environmental conditions, required availability, and the consequences of incorrect data or unavailability.
Technical analyses and checks
- Architecture is defined: acquisition, validation, storage, processing, display, and export; each interface has a format, units, time conventions, and error handling rules.
- Role-based access, traceability of changes, backups, and restoration procedures are implemented; for sensors, calibration, uncertainty, and periodic checks are specified.
- Functional requirements and defect scenarios, loss of communication, or missing data are tested; migration, integration, and reversion to a known configuration are validated.
Deliverables
Specification, architecture and interfaces, prototype or system implemented according to the contract, plan and test reports, operational, administration, and maintenance documentation.
Regulatory basis and scope
- Commission Delegated Regulation (EU) 2022/1645 — Part-IS; scope explained by EASA — Part-IS for information security risks with a potential impact on aviation safety, if the organization falls within the scope.
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR — Change management and contracted activities.
- Regulation (EU) 2017/373 — ATM/ANS common requirements and aeronautical information services — Quality and traceability requirements when the solution participates in the aeronautical data chain.
Basis condition: A record-keeping application does not become a certified CNS system through use. Functions with a safety impact require specific classification and demonstrations before operational use.
Sky Meridian Service: Hardware and software solutions · Back to table of contents
Aerodrome digital solutions: how to define requirements, data, and testing: practical article for project preparation.
19. Project management
Project management integrates scope, schedule, cost, quality, and changes through an approved baseline. Reporting must allow for decisions on critical activities and the responsibilities for unblocking them.
Input data
Contracts, brief, funding, schedule, budget, permits, deliverables, resources, and interfaces between design, verification, procurement, execution, and operation.
Technical analyses and checks
- The scope is broken down into activities and deliverables, with dependencies and acceptance criteria; the schedule distinguishes work duration from approval and access times.
- Physical and documentary progress, committed costs, and forecasts are tracked; deviations are linked to causes, effects, and measures.
- Changes are evaluated before decision-making through impact on the solution, cost, schedule, and approvals; approved revisions are distributed under control.
Deliverables
Management plan, schedule and updates, risk and change register, progress reports, record of decisions, and documents for stage acceptance.
Regulatory basis and scope
- GD No. 907/2016 — technical-economic documentation for publicly funded investments — Stages, documentation, and indicators for public investments within the scope of the decision.
- GD No. 1/2018 — contractual conditions for publicly funded investments — Mechanisms for scheduling, reporting, and administration when the contract falls under the scope of GD No. 1/2018.
- Law No. 169/2026 — Code of territorial planning, urbanism, and construction — Legal requirements regarding the realization of the investment and the responsibilities of the participants.
Basis condition: The project manager, designer, verifier, site inspector, and contract supervisor have distinct roles. The contract specifies the mandate and limits of each.
Sky Meridian Service: Project management · Back to table of contents
Project management: how to correlate schedule, costs, and decisions: practical article for project preparation.
20. Contract administration GD No. 1/2018
Contract administration tracks the application of contractual conditions to documented facts. Identify the Annex to GD No. 1/2018 used, the applicable form, and the order of precedence of the contract documents.
Input data
Contract agreement, general and special conditions, accepted offer, specifications, drawings, schedule, instructions, correspondence, work progress reports, and records contemporaneous with the events.
Technical analyses and checks
- A matrix of obligations and deadlines is constructed; notifications are correlated with the event, clause, and proof of transmission.
- For changes and claims, the cause, the invoked contractual right, the effect on the schedule, and the cost basis are analyzed; confirmed facts are differentiated from estimates.
- Approvals, payments, schedule updates, handovers, and subsequent obligations are tracked according to the contract and applicable legal framework.
Deliverables
Correspondence and deadline register, event analyses, supporting documents for notifications and claims, contractual reports, and record of decisions.
Regulatory basis and scope
- GD No. 1/2018 — contractual conditions for publicly funded investments — Annex 1 for execution or Annex 2 for design and execution, depending on the contract.
- ANAP Instruction No. 1/2021 — modification of contracts and procurement framework — Compatibility of contractual modifications with procurement legislation.
- Law No. 98/2016 — public procurement — Public procurement regime when applicable.
- Law No. 99/2016 and GD No. 394/2016 — sectoral procurement — Sectoral regime when applicable.
Basis condition: Deadlines or clause numbers from another contract are not automatically adopted. Verify the annex, special conditions, legal amendments, and the authority of the person issuing the decision.
Sky Meridian Service: Contract administration GD No. 1/2018 · Back to table of contents
GD No. 1/2018 contracts: how to document notifications, delays, and changes: practical article for project preparation.
21. Public procurement and tendering
Preparing a procurement or a tender begins with framing the procedure and translating requirements into verifiable results and evidence. Maintain consistency between the technical solution, resources, schedule, and price.
Input data
Award documentation, clarifications and amendments, technical requirements, qualification and evaluation criteria, forms, contract, quantities, deadlines, and proposed resources.
Technical analyses and checks
- For technical documentation: describe performance and acceptance criteria, correlate parts and quantities, and eliminate contradictions that may affect tendering.
- For the tender: prepare the requirement-response-evidence matrix, methodology, schedule, and resources; check the link between activities, productivity, and costs.
- Control revisions and responses to clarifications, assumptions, subcontractor responsibilities, and document completeness before submission.
Deliverables
Technical documents for award or technical proposal, compliance matrix, schedule, resource plan, verification of correlation with the financial proposal, and technical responses to clarifications.
Regulatory basis and scope
- Law No. 98/2016 — public procurement — Law No. 98/2016 and GD No. 395/2016 for public procurement.
- Law No. 99/2016 and GD No. 394/2016 — sectoral procurement — Law No. 99/2016 and GD No. 394/2016 for sectoral procurement.
- GD No. 907/2016 — technical-economic documentation for publicly funded investments — Basis and content of technical-economic documentation, when applicable.
- GD No. 1/2018 — contractual conditions for publicly funded investments — Associated contractual model, if the procurement falls within the scope of the decision.
Basis condition: The airport or utility name alone does not establish the procurement regime: verify the entity, activity, and subject of the contract. Thresholds and deadlines are taken from the legal form applicable to the procedure.
Sky Meridian Service: Public procurement and tendering · Back to table of contents
Public procurement: how to correlate the technical proposal, resources, and price: practical article for project preparation.
Defining the brief and deliverables
The contractual brief must allow for the evaluation of the proposal content and the acceptance of deliverables based on technical criteria. Specify at least:
- Subject and phases: physical and functional limits, capacities, specialties, scenarios, design phases, or evaluated processes.
- Data and studies: existing sources, additional investigations, data owners, and conditions under which these are accepted for calculation.
- Methods and references: regulatory register, analysis methods, assumptions, and acceptance criteria.
- Submission: reports, summaries, drawings, models and databases, editable or signed formats, revisions, and verification documents.
- Interfaces: responsibilities of the designer, beneficiary, verifiers, operators, and authorities; procedure for resolving observations.
- Schedule and changes: stages, dependencies, site access, submission deadlines, and handling of brief modifications.
- Costs: fee, studies, verifications, travel, external taxes, and assistance, delineated in the proposal.
Technical questions
What does the reference aircraft mean in the project?
It is the aircraft identified for supporting the analyzed verification, by type, variant, and documented parameters. Different critical conditions may result for geometry, load-bearing, or servicing; these are recorded in the design basis.
Does the geometric obstruction study demonstrate compatibility with ILS?
Geometric conclusions refer to the analyzed surfaces and criteria. Effects on LOC and GP require specific evaluation of CNS protection and, where appropriate, radio-electric basis based on data, modeling, or measurements accepted for that situation.
Can geometric shading be used as a demonstration of electromagnetic shading?
The two demonstrations have different objectives and criteria. The radio-electric analysis must address the position relative to the facility, propagation, and obstacle configuration according to the applicable methodology. The geometric conclusion is not automatically transferred to the ILS signal.
Which edition of a regulation applies?
Verify the approval act, amendments, application date, scope, and transitional provisions. For an aerodrome, add the certification basis and change regime. For internal procedures, request the controlled copy.
What else needs to be confirmed for the DANA reference?
The official AACR bibliography consulted identifies AACR-DANA-MET-CNS-02, edition 2/2018. The full text and applicable controlled revision must be confirmed before citing articles, geometric parameters, or acceptance criteria in a project's documentation.
Do regulations change between a project in Bihor and one in another county?
The national and European framework applies according to its scope. Site data, local regulations, permits, design parameters, and operator conditions may differ; these are established for each investment.
Register of normative references
The official sources below support the identification of the regulatory framework. The project-specific register complements articles, standard editions, national annexes, application dates, and references resulting from the design brief. Links to the Legislative Portal must be consulted together with the history of consolidations.
- Law No. 169/2026 — Code of territorial planning, urbanism, and construction — Applicability is established including through transitional provisions for specific documentation and procedure. Historical lists of normative acts must be re-verified after the 2026 amendments.
- NP 133-2022, vol. I — water supply systems; MDLPA Order No. 15/2023
- NP 133-2022, vol. II — sewage systems; MDLPA Order No. 14/2023
- NP 133-2022, vol. III — hydro-utility structures; MDLPA Order No. 19/2023
- I9-2022 — sanitary installations for buildings; MDLPA Order No. 2.960/2022
- MT Order No. 1.296/2017 — design, construction, and modernization of roads — Use the consolidated form and the scope corresponding to the road analyzed.
- AND 605-2016 — hot-mix asphalt — Approved by Order No. 6.970/1.779/2017, as amended, including 2023 amendments.
- NP 074-2022 — geotechnical documentation for constructions; MDLPA Order No. 27/2023
- P 100-1/2013 — seismic design of buildings; Order No. 2.465/2013 — Used with subsequent amendments and completions, including Order No. 2.956/2019; the scope targets new buildings and similar structures.
- P 118/1-2025 — fire safety of constructions; MDLPA Order No. 267/2025 — Verify the transitional provisions of the approval order and the project status.
- I 7-2011 — electrical installations for buildings; amendments via Order No. 959/2023
- GD No. 907/2016 — technical-economic documentation for publicly funded investments — Applies to investments within the scope of the decision, in consolidated form; it does not automatically constitute the framework for all private investments.
- Regulation (EU) No 139/2014 — EASA official register of aerodrome regulations — Select the provisions applicable at the date of the operation. Publication of an amendment does not mean its immediate application.
- CS-ADR-DSN, Issue 7 — certification specifications for aerodrome design — The EASA register identifies Issue 7, ED Decision 2025/004/R. The edition applicable to a work correlates with the certification basis and the change approval process.
- Regulation (EU) No 139/2014, Annex II — Part-ADR.AR
- Regulation (EU) No 139/2014, Annex III — Part-ADR.OR
- Part-ADR.OR — records, coordination, manual, and training programs
- Regulation (EU) No 139/2014, Annex IV — Part-ADR.OPS, operational requirements
- EASA — Easy Access Rules for Aerodromes, March 2026 revision — Consultation document consolidating regulations, AMC, GM, and CS. Some included texts have deferred application, e.g., amendments for ground handling applicable from 27 March 2028.
- RACR-AVZ, edition 2/2020 — Order no. 893/2020, consolidated form — Includes 2026 amendments. The object of the permit and documentation refer to the effectively proposed configuration.
- MTI Order no. 778/2026 — amendment to RACR-AVZ
- RACR-ZSAC, edition 1/2015 — MT Order no. 735/2015, as amended — The scope includes civil aeronautical servitude areas and relevant protection conditions.
- AACR Director General Decision no. D306/26.06.2020 — documentation requirements and annexes — The AACR portal indicates the application and documentation requirements, including annexes for geometric studies; select the form based on the object and phase of the request.
- AACR-DANA-MET-CNS-02 — methodology for evaluating radio-electric compatibility — The bibliography published by the AACR identifies edition 2/2018. The full text and a current controlled revision could not be verified publicly. Confirm the edition, revision, and conditions of application before use in work; do not derive numerical thresholds from secondary sources.
- Regulation (EU) 2017/373 — ATM/ANS framework and aeronautical information services — Use the AIS part and the applicable aeronautical data requirements, as amended, including those introduced by Regulation (EU) 2020/469.
- Delegated Regulation (EU) 2022/1645 — Part-IS; scope explained by EASA — Targets, among others, aerodrome operators and apron management service providers within the scope of Part-ADR.OR; analyze applicability based on the organization and information risk in question.
- GD no. 1/2018 — contractual conditions for investments financed from public funds — Annex 1: execution; Annex 2: design and execution. Identify the form applicable to the procedure and contract, with relevant amendments and transitional provisions.
- Law no. 98/2016 — public procurement — Consult the current consolidated form and the implementing rules under GD no. 395/2016.
- Law no. 99/2016 and GD no. 394/2016 — sectoral procurement — Sectoral classification depends on the entity and the activity for which the procurement is made.
- ANAP Instruction no. 1/2021 — contract modification and procurement framework — Reference for correlating contractual clauses with procurement legislation; used in conjunction with the consolidated forms of the cited acts.
Documentary revision: 14 October 2026. The AACR-DANA-MET-CNS-02 reference remains subject to confirmation of the controlled copy; the guide does not reproduce unverified internal criteria.